Project Status reports unhealthy services

Last edited: 1/15/2026

Unhealthy services in Project Status

If the project was recently restored, it can take up a couple minutes to become fully operational.

Services rely on the backend database. Unhealthy services can indicate a database being overloaded due to being undersized or not tuned appropriately.

  • Review this troubleshooting doc to determine if it could be a resource issue.
  • If services recover and become unhealthy again, there is likely a repeated issue overloading the database.

Possible resolutions: